The Ex. Engineer, Irrigation Project Majbutikaran Division Omerga And ORS v. Ranjet Rushikesh Shinde
(Order) (1) C.A. No. 1896 of 2018 & Group
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
AURANGABAD BENCH, AT AURANGABAD.
906 CIVIL APPLICATION NO.1896 OF 2018 IN FAST/38718/2017 WITH CA/1898/2018 IN FAST/38981/2017 WITH CA/1900/2018 IN FAST/38974/2017 WITH CA/1902/2018 IN FAST/38968/2017 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT MAJBUTIKARAN DIVISION, OMERGA AND OTHERS
VERSUS
KAMLAKAR TUKARAM JADHAV ..........
Advocate for Applicants : Mr. Gulab B. Rajale Advocate for Respondents : Mr. Ajit B. Kale ..........
CORAM : SMT. VIBHA KANKANWADI, J.
DATE : 09TH JULY 2019 ORAL ORDER :
Heard both sides.
02.
By these applications, the acquiring body has prayed for condoning the delay of 1136 days caused in filing first appeals.
03.
Though the applications have been strongly opposed by the respondent / respondents, on the ground that the delay of each and every day has not been explained properly, taking into consideration the contents of paras no.04 to 06, delay deserves to be condoned.
(Order) (2) C.A. No. 1896 of 2018 & Group 04.
Accordingly, the delay is condoned. The civil applications stand allowed and disposed of accordingly. Registry to verify and register the first appeals and place them for consideration on 06th January 2020.
( Smt. Vibha Kankanwadi ) JUDGE ...........
puranik / CA1896.18etc