Bombay High CourtCA/521/2025admittedallowedgrantedrule absolute
The Executive Engineer Medium Project Paranda Tq And Dist Osmanabad v. Hariba S/O Abaji Shinde Died Through Its L Rs 1 Sahebrao Hariba Shinde
2025-07-17Hon'Ble Shri Justice Shailesh P. Brahme1 pages
2025:BHC-AUG:18801 1 997 ca 521.25
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 521 OF 2025 IN FIRST APPEAL STAMP NO. 35369 OF 2024 The Executive Engineer Medium Project Paranda, Tq. and Dist. Osmanabad .. Applicant
Versus
Hariba S/o Abaji Shinde Since deceased through L.Rs.
Sahebrao Hariba Shinde and others .. Respondents Shri G. S. Khaire, Advocate h/f Shri S. S. Dande, Advocate for the Applicants.
CORAM : SHAILESH P. BRAHME, J.
DATE : 17TH JULY, 2025.
FINAL ORDER :
.
As the amount is deposited, ad-interim relief granted earlier shall stand confirmed. The civil application is disposed of. [ SHAILESH P. BRAHME J. ] bsb/July 25