The Oriental Insurance Co. Ltd., Thr Its Branch Manager, Aurangabad v. Ganpat Gopinath Gaikwad And ORS
(1) ca14433.19
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 940 CIVIL APPLICATION NO. 14433 OF 2019 IN FAST/38001/2019 THE ORIENTAL INSURANCE CO. LTD., AURANGABAD VS GANPAT GOPINATH GAIKWAD AND ORS Mr.Dhananjay P. Deshpande, Advocate for applicant Mr. Shrikant B. Madde, Advocate for the respondents CORAM :
N. J. JAMADAR, J.
DATE :
05-03-2021 P. C.
.
Heard learned counsel for the applicant-ori. Respondent No.2 and learned counsel for the respondents-ori. Claimants. 2.
This is an application for condonation of 90 days delay in preferring the appeal against the judgment and award dated 2106-2019, passed in WCA No.26/2018 by the Commissioner for Employee's Compensation & Judge, Labour Court, Latur. 3.
There is no serious objection to condone the delay. 4.
There are averments in the application which make out a sufficient cause for condonation of delay. Thus, for the reasons assigned in the application and to advance the cause of substantive
(2) ca14433.19 justice, the delay in preferring the appeal deserves to be condoned. Hence, the following order.
ORDER
i.
The application stands allowed in terms of prayer clause-B.
ii.
Delay in preferring the appeal stands condoned. iii.
The appeal be registered.
[ N. J. JAMADAR, J. ] VishalK/ca14433.19