Bombay High CourtCA/26/2018disposed offdismissed for default

The Executive Engineer, Irrigation Project Consolidation Division, Omerga And ORS v. Hari Vithal Jadhav And ANR

2018-06-15Hon'Ble Shri Justice K. K. Sonawane1 pages

1 920-CA-18-18-S

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 18 OF 2018 IN FAST/40046/2017 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT CONSOLIDATION DIVISION, OMERGA AND ORS

VERSUS

PRAKASH HARI JADHAV AND ANR ...

Advocate for Applicant No.1 : Mr. Vishal S. Badakh. AGP for Applicants No.2 and 3 : Mr. A. M. Phule. Advocate for Respondents : Mr.N.R.Pawade h/f. Mr. Laxmikant C. Patil. ...

WITH CA/20/2018 IN FAST/40155/2017 WITH CA/22/2018 IN FAST/40127/2017 WITH CA/24/2018 IN FAST/40151/2017 WITH CA/26/2018 IN FAST/40134/2017 WITH CA/28/2018 IN FAST/40122/2017 WITH CA/30/2018 IN FAST/40140/2017 WITH CA/32/2018 IN FAST/40116/2017 WITH CA/34/2018 IN FAST/40147/2017 ...

CORAM : K.K. SONAWANE, J.

DATED : 15th JUNE, 2018.

Order :- 1.

Heard learned counsel for applicants-appellants. 2.

Perused the applications and other relevant documents. 3.

There shall be stay to the execution and operation of the impugned judgment and award dated 25-11-2013 passed by the learned 2nd Joint Civil Judge, Senior Division, Osmanabad in Land Acquisition References, on condition that applicants-appellants shall deposit the entire amount of compensation pursuant to award along with accrued interest thereon in this court within a period of six weeks from today. Failure to which, the stay granted shall stand vacated automatically without further reference to the Court with liberty to the respondents-original claimants to avail the recourse of law for execution of the award within ambit of law.

4.

Accordingly, civil applications stand disposed of. [ K. K. SONAWANE ] JUDGE rrd.