Gopinath Parvat Bhusal And ORS v. The Oriental Insurance Co. Ltd., Thr Its Branch Manager And ANR
(1) 979 CA-7573.2019.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 979 CIVIL APPLICATION NO.7573 OF 2019 IN FAST/39261/2018 GOPINATH PARVAT BHUSAL AND OTHERS
VERSUS
THE ORIENTAL INSURANCE CO. LTD., THROUGH ITS BRANCH MANAGER AND ANOTHER ...
Mr. Shaikh Majit, Advocate for the applicants. ...
CORAM :
SANDIPKUMAR C. MORE, J.
DATED :
16.11.2022.
ORDER :
1.
Heard learned Counsel for the applicants - claimants. The respondents though served, but remained absent.
2.
The applicants are seeking condonation of delay of 255 days in fling the frst appeal, which appears to be caused due to their fnancial crisis. There is no oppose to the application. As such, the delay of 255 days stands condoned. 3.
The appeal be placed for admission after removal of offce objections, if any.
4.
The application is disposed of accordingly.
(SANDIPKUMAR C. MORE, J.) vd_dhirde