Executive Engineer Minor Irrigation Div., Jalna v. 1. Bhavsing Mahajan Ghunawat And ORS
2024:BHC-AUG:13096 (1) 3ca55.24speaking THIS ORDER IS CORRECTED AND UPLOADED IN VIEW OF THE ORDER DATED 02-07-2024.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 3 CIVIL APPLICATION NO. 55 OF 2024 IN FAST/37906/2023 EXECUTIVE ENGINEER MINOR IRRIGATION DIV., JALNA ....Applicant
VERSUS
1. BHAVSING MAHAJAN GHUNAWAT AND ORS .....Respondent Mr. A. D. Gade, Advocate for the applicant Mr. G. O. Wattamwar, AGP for the respondents/State Mr. Vishnu B. Madan-Patil, Advocate for respondent No.1 CORAM :
KISHORE C. SANT, J.
DATE :
20th JUNE, 2024 P. C.
1.
Heard the learned advocates for the parties.
2.
The application is preferred for condonation of delay of 549 days caused in filing the appeal.
3.
Learned advocate for the applicant submits that
(2) 3ca55.24speaking delay is caused for the reasons stated in the application that the appellant was required to complete the procedural formalities for filing the appeal. Hence, he prays to condone the delay. 4.
The application is objected by the learned Advocate for respondent No.1.
5.
However, considering the reasons stated in the application, this court is inclined to allow the application. 6.
The application stands allowed. The delay stands condoned.
7.
Office to register the appeal.
[KISHORE C. SANT, J.] VishalK/3ca55.24speaking