Executive Engineer, Irrigation Project Majbutikaran Div. Omerga Thr Mkvdc Ltd., Pune v. Shivling Rama Mule And ORS

2021-01-07Hon'Ble Shri Justice M. G. Sewlikar1 pages

( 1 ) 949 ca 6310.18

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 949 CIVIL APPLICATION NO.6310 OF 2018 IN FA/2237/2019 EXECUTIVE ENGINEER, IRRIGATION PROJECT MAJBUTIKARAN DIV. OMERGA THR MKVDC LTD., PUNE

VERSUS

SHIVLING RAMA MULE AND ORS.

...

Advocate for Applicant : Mr. S.S. Sangle ...

CORAM : M.G. SEWLIKAR, J.

DATE : 07.01.2021 P.C.:- Since the entire amount of compensation is deposited, interim relief is granted in terms of prayer clause ' B'

. Civil Application is disposed of.