IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD WRIT PETITION NO. 15564 OF 2019 Shankar Parvati Multi Projects Through its Proprietor Vaibhav Chaburao Jadhav .. Petitioner

Versus

The State of Maharashtra and others .. Respondents Mr. S. D. Tawashikar h/f Vishnu Y. Patil, Advocate for Petitioner. Mr. S. B. Pulkundwar, AGP for Respondents-State. CORAM : S. V. GANGAPURWALA & MANGESH S. PATIL, JJ.

DATED : 02nd JANUARY, 2020.

PER COURT:- .

Heard the learned counsel for the petitioner. 2.

The learned counsel for the petitioner submits that respondent No. 2 be directed to complete further tender process immediately within a week. After opening the technical bid, financial bid has to be opened within a period of seven days. The Government Resolution prescribes the time frame.

3.

Mr. Pulkundwar, learned AGP on instructions submits that some of the tenderers had raised objection to the documents submitted by the petitioner. The said documents are sent for verification, in view of

2 38-WP15564-19.odt that process is delayed.

4.

As on date, the petitioner does not have a vested right. The documents of the petitioner are sent for verification as contended by the learned AGP.

5.

In view of the above, no further orders are necessary in the present matter. Writ petition is disposed of. No costs. ( MANGESH S. PATIL ) ( S. V. GANGAPURWALA ) JUDGE JUDGE P.S.B.