← Library
Bombay High CourtCA/10207/2021delay condonatedrejected

The Ex. Engineer, Medium Project Division, Latur And ANR v. Bhalchandra Lalasaheb More

2022-09-19Hon'Ble Shri Justice Sandipkumar C. More1 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD 35 CIVIL APPLICATION NO.10207 OF 2021 IN FAST/40711/2019 THE EX. ENGINEER, MEDIUM PROJECT DIVISION, LATUR AND ANOTHER

VERSUS

BHALCHANDRA LALASAHEB MORE ...

Advocate for Applicants : Mr. Anand P. Raka h/f. Mr. Munde Suresh W.

Advocate for Respondent : Mr.

Vikas G. Kodale h/f. Mr. Gunale V.D.

...

CORAM : SANDIPKUMAR C. MORE, J.

DATE : 19.09.2022 PER COURT :

.

Heard rival submissions. The applicant- appellant Acquiring Body is seeking condonation of delay of 2128 days which appears to be resulted due to time spent in obtaining approvals at various stages. In view of the same, the delay of 2128 days stands condoned. 2.

The appeal be placed for admission after removal of office objections, if any.

3.

The application is accordingly disposed of.

(SANDIPKUMAR C. MORE) JUDGE .....

shp/-