IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR.

Civil Application No.8/2015 in C.P.No.133/2014 in LPA No.279/2013 in Writ Petition No. 4790/2006.

(Ramesh Vithobaji Bhendare and ors. .vs. Shri S.G. Dhawale, the Executive Engineer, Wardha Irrigation Project, Wardha ) ------------------------------------------------------------------------------------------------------------- --- Office Notes, Office Memoranda of Coram, appearances, Court's orders or directions Court's or Judge's orders.

and Registrar's orders Mr. A.I. Sheikh, Advocate for Petitioners.

Mr. Mehroz Pathan, AGP for Respondent.

CORAM : B.R. Gavai & Mrs. Mridula Bhatkar, JJ.

DATED : February 27, 2015.

The learned AGP placed on record the order dated 23.2.2015 vide which all the applicants are directed to be reinstated and 25% of the back-wages are being paid to them. Insofar as the employees who have attained the age of 60 years are to be treated as superannuated and 25 % of the back-wages till the date of their superannuation will be paid. However, undisputedly the actual amount of back-wages are not paid to them.

Mr. Pathan, learned AGP appearing on behalf of the respondent on instructions from Mr. S.G. Dhavale, Executive Engineer, Irrigation Project, Wardha, makes a categorical statement that the part of the back-wages would be paid within a period of one week and the remainder within a period of one month from today. We, therefore, grant time till 6.5.2015 for

CAN8-15.odt making the payment of back-wages.

Stand over to 6.5.2015.