Vidarbha Irrigation Development Corporation Thr. Executive Engineer v. Dnyneshwar Uttamrao Chore And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR CAF No.964/2013 in FA St. No.648/2013 VIDC VS. Dnyaneshwar Uttamrao Chore and others. ----------------------------------------------------------------------------------- Notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's or directions and Registrar's orders.
Orders.
CORAM : Z.A. HAQ, J DATE : 6th January, 2015.
Heard Shri Agrawal, the learned Advocate holding for Shri P.B. Patil, the learned Advocate for the applicant. None appears for the non-applicants.
The learned Advocate for the applicant submits that the applicant-VIDC was not impleaded as party to the proceedings and therefore, the delay has occasioned.
I am satisfied that the cause shown by the applicant is justifiable. The delay of 276 days is condoned. The application is allowed.
JUDGE Ambulkar