V. I. D. C. Chandrapur Through Executive Engineer, Chandrapur Medium Project Dn. No. 1 And Another v. Sau. Kamlabai W/O Wamanrao Ingle And 2 Others
6-bcaf223.18.odt 1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR CIVIL APPLICATION (CAF) NO. 595/2018 IN FIRST APPEAL STAMP NO. 233/2018 V.I.D.C. Through Executive Engineer, Chandrapur Medium Project Division No.1, Chandrapur and another.
V/s Sau. Kamlabai w/o Wamanrao Ingle and others.
--------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoramda of Coram, appearances, Court's orders of directions Court's or Judge's orders.
and Registrar's Orders.
--------------------------------------------------------------------------------------------------------------------------------- Shri J.J. Alkari, counsel for the appellant.
Shri S.S. Joshi, counsel for the respondent No.1. Shri S.D. Sirpurkar, AGP for the respondent Nos. 2 and 3. CORAM: ARUN D. UPADHYE , J.
DATE: 22-01-2019.
Perused the application. It appears that delay is of 2353 days in filing the appeal. Though, the delay is inordinate one, this Court has condoned the delay in First Appeal Nos. 1180/2018 and 1308/2018. On the ground of parity, the delay in filing the appeal in the present case also be condoned. For the reasons stated in the application, the delay is condoned. The civil application is allowed. CIVIL APPLICATION (CAF) NO. 223/2018 Heard learned counsel for the parties.
Perused the application. For the reasons stated in the application, the appellant could be permitted to prefer the appeal. Hence, the civil application is allowed.
6-bcaf223.18.odt 2 FIRST APPEAL STAMP NO. 233/2018.
Heard.
Admit.
Call for record and proceedings.
Learned counsel Shri S.S. Joshi, waives notice for the respondent No.1.
Learned Assistant Government Pleader Shri S.D.Sirpurkar, waives notice for the respondent Nos. 2 and 3.
JUDGE rkn