← Library
Bombay High CourtCAF/365/2016ca disposed off

General Manager, Central Railway C.S.T. Mumbai Through Dy. Chief Engineer, (Construction) v. Ku. Rupali Dalpatbhai Mehta And Others

2016-04-28Hon'Ble Shri Justice A.S. Chandurkar1 pages

8-CAF-365-16 1/1

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

CIVIL APPLICATION NO.365 OF 2016 IN FIRST APPEAL NO.537 OF 2015 General Manager, Central Railway, C.S.T. Mumbai Thr. Dy. Chief Engineer, (Construction) Central Railway, Nagpur.

-vs- Rupali Dalpatbhai Mehta and ors.

------------------------------------------------------------------------------------------------------------------------------------ Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.

or directions and Registrar's orders.

Shri R. G. Agrawal, Advocate for appellant.

Shri S. S. Alaspurkar, Advocate for respondent No.1/applicant. Shri H. R. Dhumale, AGP for respondent No.2/State. CORAM : A.S.CHANDURKAR, J.

DATE : April 28, 2016 Perused the judgment of the Reference Court. The claimant is permitted to withdraw 50% of the amount of enhanced compensation on filing undertaking that in case the appeal is allowed, the amount withdrawn shall be repaid with interest at such rate the Court may direct. The remaining 50% amount is permitted to be withdrawn on furnishing solvent surety/security to the satisfaction of the Registrar (Judicial). The amount be paid to the Power of Attorney holder of the respondent No.1 as requested. Civil application is allowed and disposed of. JUDGE Asmita