Vidarbha Irrigation Development Corp. Thr. Executive Engineer, Nagpur Irrigation Division (South) v. Shri Damodar Vithoba Chandekar (Dead) Thr. Lrs. Dilip Damodar Chandekar And Others
HIGH COURT LEGAL SERVICES SUB-COMMITTEE, NAGPUR BENCH, NAGPUR.
BEFORE THE NATIONAL LOK ADALAT FIRST APPEAL NO. 63 of 2018 V.I.D.C. thr Executive Engineer, Nagpur Irrigation Divn (South), Nagpur
Versus
Shri Damodar vithoba Chandekar (dead) thr LRS & ors. Smt. U.A. Patil, counsel for the appellant.
Shri I.J. Damle, Asst. G.P. For Respondent No 8.
ORDER
(Passed on 17thMarch, 2019) Shri G.G. Dhawale, Executive Engineer, Nagpur Irrigation Divn.( South) Nagpur is present. The appellant has tendered pursis today, which is marked as "X" for identification. The instant appeal is covered under the Government Regulations dated 3rdNovember, 2016 and 23rd February, 2017 and therefore, the appellant seeks permission to withdraw the appeal. The appeal stands disposed of as withdrawn in terms of pursis Exh. 'X'. No Costs. The remaining amount, if any, shall be deposited by the appellant before the reference Court within three months from the date of Award.
The respondents/claimants shall be entitled to withdraw the amount of compensation, if any deposited in the High Court / Reference Court, alongwith accrued interest. Court fees, if any, be refunded to the appellant as per rule. MEMBER MEMBER PRESIDING OFFICER (M.P. Munshi) (G.M. Kubde) (Justice Rohit B. Deo) Advocate Retd. P.D.J.
rsb