← Library
Bombay High CourtFA/572/2009dispossed offdismiss for default

V.I.D.C., Through Executive Engineer, Minor Irrigation Lower Pus Project Division, Pusad v. Pradeep Narayan Dange, And 2 Others

2015-05-08Hon'Ble Shri Justice A.S. Chandurkar1 pages

fa572.09

IN THE HIGH COURT OF JUDICATURE AT BOMBAY,

NAGPUR BENCH, NAGPUR FIRST APPEAL NO.572 OF 2009 V.I.D.C., THROUGH EXECUTIVE ENGINEER, MINOR IRRIGATION LOWER PUS PROJECT DIVISION, PUSAD V/S PRADEEP NARAYAN DANGE, AND 2 OTHERS ....................................................................................................................................................... Office Notes, Office Memoranda of Coram, appearances, Court orders or directions Court's or Judge's Order and Registrar's orders ....................................................................................................................................................... Shri A.B. Patil, counsel for the Appellant.

Shri Taj M. Malnas, counsel for R-1.

Mrs. N.M. Hiwase, AGP for R-2 & 3.

CORAM

: A.S. CHANDURKAR, J.

DATED : MAY 8, 2015 Heard.

The appellant and the respondent No.1 have jointly filed Pursis vide St. No.5086 of 2015 stating therein the matter has been compromised between the parties.

The respondent No.1 - claimant is present before this Court and is identified by his learned counsel. The Pursis is signed by the respective parties and their learned counsel. Considering the terms of compromise, the first appeal stands disposed of as per the terms specified in clause Nos.(i) to (iv) of the Pursis.

The amount agreed to be paid by the appellant shall be paid within a period of three months from today. Decree be drawn accordingly. No costs.

JUDGE !! BRW !!

...../-