Executive Engineer, Minor Irrigation Division, V. I. D. C., Washim v. Motiram Namdeo Sabale And 2 Others
924-FA-943-7 1/1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (CAF) NO.398 OF 2019 IN FIRST APPEAL NO.943 OF 2017 V.I.D.C. Thr. Executive Engineer, Minor Irrigation Division, Washim -vs- Motiram Namdeo Sabale and ors.
------------------------------------------------------------------------------------------------------------------------------------ Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.
or directions and Registrar's orders.
Smt. U. A. Patil, Advocate for appellant.
Shri Amol Darekar, Advocate for respondent No.1/applicant.
Ms M. S. Naik, AGP for respondent Nos.2 and 3. CORAM : A.S.CHANDURKAR, J.
DATE : January 30, 2019 Heard the learned counsel and perused the impugned judgment.
Considering the nature of evidence on record, claimant is permitted to withdraw 50% of the amount of compensation as deposited on filing undertaking within period of eight weeks that in case the appeal is allowed, said amount shall be repaid with interest at such rate the Court may direct. Further 25% amount of compensation is permitted to be withdrawn on furnishing surety/security to the satisfaction of the Registrar (Judicial). Remaining amount shall be invested in fixed deposit.
Civil application is disposed of.
JUDGE Asmita