Maha. State Power Generation Co. Ltd., Thr. By. Executive Engineer, Paras, Akola v. Mohd. Ayyaz Ab. Munaf And Others
2024:BHC-NAG:3145 1 caf 301.2024.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH, AT NAGPUR.
Civil Application (CAF) No. 301 of 2024 in First Appeal No.
of 20 [Maharashtra State Power Generation Co. Ltd. Through its Dy. Executive Engineer, Paras, Tehsil Balapur, Dist. Akola ..vs.. Mohd. Ayyaz Ab. Munaf and ors.] - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Mr. N. G. Moharir, Advocate for the applicant/appellant Mr. S. S. Sohoni, Advocate for respondent nos. 1 to 3 CORAM : ANIL L. PANSARE J .
DATED : 14-03 -202 By present application, which has been filed on 25-1-2024, the applicant/appellant is seeking extension of time to deposit the decreetal amount.
Vide order dated 30-8-2023, this Court has granted stay to the execution of the judgment and award dated 16-2-2023 subject to depositing entire amount of compensation within eight weeks, which period concludes sometimes on 26-10-2023.
The applicant/appellant ought to have filed application seeking extension prior to lapsing of time which the applicant/appellant has not done. Therefore, the time cannot be extended as prayed for.
2 caf 301.2024.odt Learned counsel for the appellant submits that cheque of decreetal amount is ready and accordingly seeks permission to deposit the same. Permission is granted. Decreetal amount be deposited within one week from today.
(Anil L. Pansare, J.) wasnik