← Library
Bombay High CourtFA/91/2017withdrawn

Vidarbha Irrgation Development Corporation, Through Its Executive Engineer, Wardha v. Vishal Shailendra Jaiswal, And 3 Others

2019-07-13Lok - Adalat1 pages

HIGH COURT LEGAL SERVICES SUB-COMMITTEE, NAGPUR BENCH, NAGPUR. BEFORE THE NATIONAL LOK ADALAT FIRST APPEAL NO.91 OF 2017 VIDC thr. its Executive Engineer, Lower Wardha Project Division, Wardha, Tah. & Dist. Wardha.

Versus

Vishal Shailendra Jaiswal & ors.

Shri S. K. Bhoyar Advocate for appellant.

Mrs. Shamshi Haider, A.G.P. for respondent Nos. 3 & 4.

ORDER

(Passed on 13th July 2019) Shri R. P. Varade, Executive Engineer, Lower Wardha Project Division, Wardha is present.

The appellant has tendered pursis today, which is marked as "X" for identification.

The instant appeal is covered under the Government Regulations dated 3rdNovember, 2016 and 23rd February, 2017 and therefore, the appellant seeks permission to withdraw the appeal.

The appeal stands disposed of as withdrawn in terms of pursis Exh. 'X'. No Costs.

The appellant shall deposit the amount of compensation before the reference Court within a period of three months from the date of award. The respondent/claimant shall be entitled to withdraw the amount of compensation, if deposited in the reference Court/High Court, alongwith accrued interest.

Court fees, if any, be refunded to the appellant as per rule. MEMBER MEMBER PRESIDING OFFICER (A.R. Patil) (G.M. Kubde) (Justice Vinay Joshi) Advocate Retd. P.D.J.

Gohane