Exe. Engineer, Purna Medium Project Achalpur Div. (Now Medium And Minro Irrigation Div., Achalpur) v. Sudhir S/O Dadarao Wankhade And Others
936 CAF-1108-2022
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (F) NO.1108 OF 2022 IN FIRST APPEAL (ST) NO.2067 OF 2022 {Executive Engineer ..Vrs.. Sudhir s/o Dadarao Wankhade and Ors.} ______________________________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's order and Registrar's orders.
Shri J. B. Kasat, Advocate for the Applicant/Appellant. Shri R. J. Shinde, Advocate for the Respondent No.. Ms T. H. Udeshi, AGP for the Respondents No.2 and 3. CORAM : ABHAY AHUJA, J.
DATE : 18 th OCTOBER , 202 2 .
.
This is an application seeking condonation of delay of 1776 days in preferring an appeal against the judgment and award dated 04.02.2015, passed by the Joint Civil Judge Senior Division, Achalpur in Land Acquisition Case No.16 of 2007.
2.
Shri Kasat, learned counsel for Applicant/Appellant draws the attention of this Court to the application for condoning the delay as well as relies upon the decision of this Court dated 18.10.2022, in Civil Application (F) No.1104 of 2022 in First Appeal St. No.2040 of 2022.
3.
Shri Shinde, learned counsel for Respondent No.1 and Ms Udeshi, learned Assistant Government Pleader for Respondents No.2 and 3 have no objection if the delay is condoned.
4.
For the reasons stated in the order of this Court dated 18.10.2022, the delay of 1776 days is hereby condoned.
936 CAF-1108-2022 5.
The civil application accordingly stands disposed. (JUDGE) TAMBE ASHOKRAO TAMBE Personal Assistant to Hon'ble JUDGE