Vidarbha Irrigation Development Corporation Thr. Executive Engineer, Minor Irrigation Works v. Dhanraj Mahadeo Warghane And Another
630.17ca (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT NAGPUR CIVIL APPLICATION NO. 630 OF 2017 IN FIRST APPEAL NO. 456 OF 2013 Vidarbha Irrigation Development Corporation, through its Executive Engineer, M.I. Works, Wardha.
..APPELLANT
VERSUS
Dhanraj Mahadeo Warghane & anr ..RESPONDENTS Mr P.B. Patil, Advocate for appellant;
Mr C.R. Rajbile, Advocate for respondent No.1; Mr M.A. Kadu, A.G.P. for respondent No.1 CORAM : N.W. SAMBRE, J.
DATE : 10th APRIL, 2017 ORAL ORDER :
The applicant-claimant has already withdrawn 50% of the decretal amount, which was already deposited. The acquiring body thereafter deposited remaining 50% amount, of which withdrawal is sought.
2.
The claim of withdrawal of the amount is objected.
630.17ca (2) 3.
In the interest of justice, the applicant is permitted to withdraw 50% of the amount deposited in this Court upon filing of usual undertaking to the satisfaction of the Registrar (Judicial) of this Court.
4.
Civil Application stands disposed of.
5.
With the consent of the parties, the matter be placed in next National Lok Adalat. (N.W. SAMBRE, J.) Tupe