General Manager, Central Railway Through Dy. Chief Engineer Construction v. Smt. Bharti Nandkishore Patil And Another
2025:BHC-NAG:2729 3 CAF-681-2025
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (F) NO.681 OF 2025 IN FIRST APPEAL NO.701 OF 2014 [General Manager, Central Railway ..Vs.. Smt. Bharati Nandkishor Patil and Anr.] ______________________________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's order and Registrar's orders.
Mr N. P. Lambat, Advocate for Applicant/Appellant. Mr V. S. Giramkar, Advocate for Non-Applicant/Respondent No.1. Mr S. C. Joshi, AGP for Respondent/State.
CORAM
: M. W. CHANDWANI, J.
DATE : 18 th MARCH , 2025 .
1.
Since the appeal filed by the appellant has already been dismissed by this Court, therefore, the respondent No.1 is entitled to the decreetal amount deposited by the appellant in this Court.
2.
The respondent No.1 is permitted to withdraw the amount of Rs.1,25,748/- alongwith accrued interest. 3.
The application stands disposed of accordingly. JUDGE Tambe