Ramakant S/O. Tribhuwannath Tiwari v. Nagpur Improvement Trust, Thr. Its Chairman, Nagpur And Others
2025:BHC-NAG:1761-DB 1 942.pil.36.24
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAO) No.144/2025 IN PUBLIC INTEREST LITIGATION NO. 36/2024 Ramakant s/o. Tribhuwannath Tiwari Vs.
Nagpur Improvement Trust, Nagpur and Ors.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - Mr. G. I. Dipwani, Advocate for Petitioner.
Mr. G. A. Kunte, Advocate for Respondent Nos.1 and 3. Mr. N. S. Rao, A.G.P. for Respondent Nos.2 & 4/State. Mr. N. S. Deshpande, DSGI for Respondent No.5. Mr. S. R. Kubhalkar, Advocate h/f. Mr. P.S. Tiwari, Advocate for Intervenor.
Mr. P. M. Jain, Advocate h/f. Mr. M. R. Johrapurkar, Advocate for Intervenor.
CORAM : NITIN W. SAMBRE AND MRS.VRUSHALI V. JOSHI, JJ.
DATED : 20/02/2025.
.
Leave is granted to amend the cause title of Civil application (CAO) Nos.1114/2024 and 1115/2024 so as to add legal representatives of deceased applicant No.1 in the above applications.
2.
The amendment to be carried out forthwith.
3.
The Civil Application No.144/2024 stands disposed of.
PUBLIC INTEREST LITIGATION NO. 36/2024 4.
Mr. N. S. Rao, learned Assistant Government Pleader appearing for respondent Nos.2 and 4 seeks time to file affidavit in reply.
5.
In response to the Court's query, we are informed by the learned Counsel appearing for the
2 942.pil.36.24 petitioner, so also respondent Nos.1 and 3 Mr. Kunte that the order dated 23.08.2024 be corrected and it be observed that Mr. Kunte waives service of notice for respondent Nos.1 and 3 and Assistant Government Pleader waives service of notice for respondent Nos.2 and 4. 6.
We also direct the respondent No.3 to file affidavit-in-reply dealing with the issue involved in the petition.
7.
We further direct the Executive Engineer, Public Works Department, who is executing the project in question, to remain present on the next date of hearing. 8.
Stand over to 06.03.2025.
(MRS. VRUSHALI V. JOSHI, J.) (NITIN W. SAMBRE, J.) RGurnule