Executive Engineer, Lower Wardha Project Division v. Prakash Gangadharrao Raut And 2 Others
933-CAF-1032-17 1/1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (CAF) NO.1032 OF 2017 IN FIRST APPEAL NO.71 OF 2016 Executive Engineer, Lower Wardha Project Dvn. Wardha -vsPrakash Gangadhar Raut and ors.
----------------------------------------------------------------------------------------------------------------------------------- - Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.
or directions and Registrar's orders.
Shri P. B. Patil, Advocate for appellant.
Shri A. R. Ingole, Advocate for respdt. No.1/applicant. Ms H. N. Prabhu, AGP for respondent Nos.2 and 3. Ms CORAM : A.S.CHANDURKAR, J.
DATE : March 03, 2017 The claimant seeks permission to withdraw the amount of compensation deposited by the appellant.
Perused judgment of the Reference Court. Considering the reasons the claimant is permitted to withdraw an amount of Rs.10 lakhs subject to filing an undertaking that in case the appeal is allowed, said amount shall be repaid with interest at such rate the Court may direct. Further amount of Rs.10 lakhs is permitted to be withdrawn on furnishing solvent surety/security to the satisfaction of the Registrar (Judicial). The remaining amount shall be invested in Fixed Deposit.
Civil application is allowed and disposed of. JUDGE Asmita