IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR Civil Application (CAF) No.845/2021 IN First Appeal Stamp No.4798/2021 VIDC through its Executive Engineer, Bembla Project, Yavatmal Vs. Sau. Rajani Ravindra Dhawale & Ors.

************************************************************************************************************* Office notes, Office Memoranda of Coram, appearances, Court'

s orders Court's or Judge's Orders or directions and Registrar's orders.

************************************************************************************************************* Shri M.A. Kadu, Advocate for the Applicant.

Ms. Hemlata Jaipurkar, AGP for Respondent Nos.2 and 3. CORAM : S.M. MODAK, J.

DATE : 21 st APRIL, 2021.

Hearing was conducted through Video Conferencing and the learned Advocate agreed that the audio and visual quality was proper.

There is delay of 607 days in preferring an appeal against the judgment of the reference Court.

Issue notice to the respondents, returnable after twelve weeks subject to removal of office objections within a period of two weeks.

Ms. Hemlata Jaipurkar, learned AGP waives service of notice on behalf of respondent Nos.2 and 3.

Civil Application (CAF) No.846/2021 The appellant is ready to deposit the entire decretal amount before this Court within a period of twelve weeks. In view of this, stay is granted to the execution of the impugned judgment and decree subject to deposit of entire decretal

23.FAST.4798.2021.

2/2 amount before this Court within a period of twelve weeks. The civil application is disposed of.

The original claimant is at liberty to ask for withdrawal. JUDGE vijay