Bombay High CourtCAO/708/2018admittedallwdgrantedrule absolute

Vitthal Tukaram Bhakre v. Executive Engineer, Medium Project Division, Yavatmal And Others

2018-09-05Hon'Ble Shri Justice Z.A. Haq1 pages

1 cao708.18

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAO) NO.708 OF 2018 IN XOB NO. OF 2016 IN FIRST APPEAL NO.671 OF 2015 (VITTHAL TUKARAM BHAKRE...VS.. EXECUTIVE ENGINEER, MINOR IRRIGATION DN VIDC & OTH.) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri R.C.Raibhandare, Advocate for Appellant Shri H.D.Dube, A.G.P. for Respondent Nos.2 & 3. Shri A.B.Nakshane, Advocate for Respondent No.1/Objector. CORAM : Z.A.HAQ, J.

DATED : SEPTEMBER 05, 2018.

For the reasons stated in the application delay of 83 days in filing the cross objection is condoned. The Civil Application is allowed. No costs.

CROSS OBJECTION ST.NO. 5865/2018.

ADMIT Shri R.C.Raibhandare, Advocate waives notice for the appellant and Shri H.D. Dube, A.G.P. waives notice for the respondent Nos. 2 and 3.

The appellant-Executive Engineer, Minor Irrigation Division, VIDC, Yavatmal shall file private paper book within six months. Memo of Cross-objection be included in the paper book.

JUDGE RRaut..