Vidarbha Irrigation Development Corp. Thr. Its Executive Engineer, Lower Wardha Project Division v. Sadhana Sharad Shende And 2 Others
2604caf1263.16
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
APPELLATE SIDE NAGPUR BENCH, NAGPUR CIVIL APPLICATION (CAF) NO. 1263 OF 2016 IN FIRST APPEAL NO. 342 OF 2015 VIDC Wardha Vs. Sadhana Sharad Shende & Ors. ........................................................................................................................................................................ Office Notes, Office Memoranda of Coram, appearances, Court orders or directions Court's or Judge's Order and Registrar's orders ........................................................................................................................................................................ Shri J. B. Kasat Adv for appellant.
Shri V. S. Kukday, Adv for respondent 1.
Shri H. R. Dhumale AGP for respondents 2 & 2. CORAM: A. S. CHANDURKAR J.
DATED: 26th t APRIL, 2016.
Prayer is to permit the claimants to withdraw the amount of compensation deposited by the appellant.
Perused the judgment of the Reference Court. The claimant is permitted to withdraw amount of Rs. 5,00,000/- on filing undertaking that in case the appeal is allowed the amount withdrawn shall be repaid with interest at such rate the Court may direct. Balance amount is permitted to be withdrawn on furnishing solvant security/surety to the sarisfaction of the Registrar (Judicial) High Court Nagpur. Civil application is disposed of JUDGE svk