← Library
Bombay High CourtCAF/1415/2016admittedallwdgrantedrule absolute

Maharashtra Industrial Development Corporation Throgh Its Chief Executive Officer, Amravati v. Bhikari Dhanu Jadhao And 2 ORS.

2016-10-26Hon'Ble Shri Justice Z.A. Haq1 pages

1 caf1415.16

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO.1415 OF 2016 IN FIRST APPEAL NO. 243 OF 2016 (MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPN....VS.. BHIKARI DHANU JADHAV & OTH.) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri M.M.Agnihotri, Advocate for Appellant/Applicant. Shri D.G.Patil, Advocate for Respondent No.1/Claimant. Ms S.Z.Haider, A.G.P. for Respondent Nos. 2 & 3. CORAM : Z.A.HAQ, J.

DATED : OCTOBER 26, 2016.

The learned advocate for the appellantCorporation states that the amount of compensation will be deposited by tomorrow as the Demand Draft is with him. The Regional Officer has filed affidavit pointing out the circumstances because of which there is delay in depositing the amount of compensation.

The appellant is permitted to deposit the amount of compensation within two weeks.

On deposit of the amount, it be given to the respondent No.1/Claimant.

The civil application is allowed in the above terms.

JUDGE RRaut..