Executive Engineer, Minor Irrigation Department, Man Project Div., Khamgaon v. Govt. Of Maharashtra, Through District Collector, Buldhana And Others
1 2704caf1282.16
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (F) NO.1282 OF 2016.
IN FIRST APPEAL NO.973 OF 2015 EXECUTIVE ENGINER MINOR IRRIGATION DEPARTMENT BULDANA VS GOVT. OF MAHARASHTRA AND OTHERS - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri P. B.Patil, Advocate for the appellant.
Shri H. R. Dhumale, Asstt. Government Pleader for respondent Nos.1 & 2. Shri R. P. Masurkar, Advocate for respondent No.3. CORAM : A.S. CHANDURKAR, J.
DATED : APRIL 27, 2016.
Prayer is to permit the claimants to withdraw the amount of compensation. The appellant has deposited 75% of the decreetal amount as directed by this Court. Perused the judgment of the Reference Court.
50% of the amount deposited is permitted to be withdrawn on filing an undertaking that in case the appeal is allowed, the said amount shall be repaid with interest at such rate the Court may direct. The remaining 50% amount deposited is permitted to be withdrawn on furnishing solvent surety/security to the satisfaction of the Registrar (Judicial). Civil application is disposed of.
JUDGE /MULEY/