New India Assurance Co. Ltd., Thr. Chief Regional Manager, Nagpur v. Vithal S/O Dasiba Nindekar And Others
34.caf.527.23.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION NO.
OF 202 3 IN MISC. CIVIL APPLICATION (ST.) NO.6458 OF 2023 I N FIRST APPEAL (ST.) NO.
OF 20 (The New India Assurance Co. Ltd. Vs. Vithal s/o Dasiba Nindekar and ors.) -------------------------------------------------------------------------------------------------------- Office Notes, Office Memoranda of Court's or Judge's Order Coram, appearances, Court's Orders or directions and Registrar's order --------------------------------------------------------------------------------------------------------- Shri A.W. Paunikar, Advocate for the appellant. CORAM:- URMILA JOSHI-PHALKE, J.
DATED :- APRIL 11, 2023.
Heard.
2.
This is an application for condonation of delay which is caused in filing the restoration application. 3.
As per the contention of the appellant that the Registrar (J.) has passed the order to remove the office objections within 14 days which was inadvertently not noted by the learned Counsel for the appellant, and therefore, the delay is caused.
4.
In view of the reasons mentioned in the application, the delay of 174 days is condoned. 5.
Civil application is disposed of.
MISC. CIVIL APPLICATION (ST.) NO.6458 OF 2023 On removal of office objections within two weeks, the appeal be restored at its original stage. On failure to remove the office objections, the order passed by the Registrar (J.) will survive.
2.
The application is disposed of.
Signed By:DIVYA SONU BALDWA Personal Assistant (URMILA JOSHI-PHALKE, J.) *Divya