V.I.D.C. Thr. Exe. Engineer, Bembla Canal Project, Yavatmal v. Smt. Anusaya Sudhakar Jaysingkar And Others
2024:BHC-NAG:6906 11..odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR C IVIL APPLICATION (CAF) NO.
OF 2022 IN FIRST APPEAL ST. NO.6065 OF 2021 V.I.D.C. through Executive Engineer, Yavatmal .Vs. Smt. Anusaya Sudhakar Jaysingkar and others Office Notes, Office Memoranda of Court's or Judge's Order Coram, appearances, Court's Orders or directions and Registrar's order Shri C.J. Dhumane, Advocate for appellant.
Shri P.P. Pendke, A.G.P. for respondent Nos.2 and 3/State. CORAM : SANJAY A. DESHMUKH , J.
DATED : 03/07/ 1.
This is an application for condonation of delay of 258 days caused for filing of appeal under Section 5 of the Limitation Act.
2.
Heard both the sides.
3.
For the reasons stated in the application, the application is allowed in the interest of justice. 4.
The delay caused in filing the appeal is condoned.
5.
Civil application is disposed of accordingly. FIRST APPEAL ST. NO.
OF 2021 6.
Issue notice to the respondents, returnable after four weeks.
7.
Shri Pendke, learned A.G.P. waives service of notice for the respondent Nos.2 and 3.
8.
Call record and proceedings.
(SANJAY A. DESHMUKH, J.) C.L. Dhakate