← Library
Bombay High CourtCAF/1602/2019admittedallwdgrantedrule absolute

Vidarbha Irrigation Development Corp Thr. Exe. Engineer, Canal Div. Bembla Project, Yavatmal And An v. Raju Devrao Shivankar And Others

2019-04-15Hon'Ble Shri Justice Arun Digambarrao Upadhye2 pages

19caf1602.19.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH AT NAGPUR CIVIL APPLICATION (CAF) NO. 1602/2019 IN FIRST APPEAL STAMP NO. 6553/2018 Executive Engineer, Bembla Project Division, Yavatmal. ...Versus...

Raju Devrao Shivankar and others.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri M.A. Kadu, learned counsel for the appellant. Ms. V.S. Mohod, learned counsel for the respondent No.1. Ms H.N. Jaipurkar, AGP for the respondent No.2 and 3. CORAM : ARUN D. UPADHYE, J.

DATE : 15/04/2019.

Heard learned counsel for the respondent No. 1. Perused the application. It appears that part amount of compensation is deposited before the Reference Court and part amount deposited in this Court. At the most, respondent No.1 is permitted to withdraw the amount deposited by the appellant in this Court on furnishing usual undertaking.

Hence, I pass the following order:-

ORDER

i] Civil application is partly allowed.

ii] The respondent No.1 is permitted to withdraw the

19caf1602.19.odt amount of Rs.1,98,289/- with accrued interest deposited in this Court on filing usual undertaking to the effect that he will refund the amount, in case appeal is allowed. JUDGE rkn