Vidarbha Irrigation Development Corporation, Through The Executive Engineer, Wardha And 1 v. Harikisan Jitmal Gandhi And 2 Others
cao918.15
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH, NAGPUR CAO NO.918 OF 2015 WITH MCA ST.NO.9291 OF 2015 IN REJ. F.A. NO.613 OF 2014 VIDARBHA IRRIGATION DEVELOPMENT CORPORATION, THROUGH THE EXECUTIVE ENGINEER, WARDHA AND ANR V/S HARIKISAN JITMAL GANDHI AND OTHERS ....................................................................................................................................................... Office Notes, Office Memoranda of Coram, appearances, Court orders or directions Court's or Judge's Order and Registrar's orders ....................................................................................................................................................... Shri S.S. Godbole, counsel for the applicants/appellants. Mrs. N.M. Hiwase, AGP for R-2 & 3.
CORAM
: A.S. CHANDURKAR, J.
DATED : MAY 8, 2015 Heard.
For the reasons mentioned in the application, delay in filing the restoration application stands condoned. The civil application is allowed and disposed of. MCA ST.NO.9291 OF 2015 Heard.
For the reasons mentioned in the application, the order of dismissing of the appeal is recalled. However, objections be removed within a period of six weeks from today. The applicant / appellant to pay the costs of Rs.500/- to the High Court Legal Services Sub Committee, Nagpur within the aforesaid period. If these directions are not complied .....2/-
cao918.15 with, earlier order dismissing of the appeal shall revive. The misc. civil application is disposed of accordingly.
Civil Application St.No.11107 of 2014 Heard.
Upon appellants' depositing the entire amount of enhanced compensation in this Court within a period of ten weeks from today, the execution of the impugned judgment shall remain stayed until further orders.
Put up after ten weeks.
JUDGE !! BRW !!
...../-