IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

CIVIL APPLICATION (CAF) NO.2172 OF 2014 IN FIRST APPEAL (ST) NO.10108 OF 2014 V.I.D.D. Thr. Its Exe. Engineer, Bembla Project Dvn. -vsHaribhau S/o Wamanrao Thakare & Ors.

---------------------------------------------------------------------------------------------------------------------------------- Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.

or directions and Registrar's orders.

---------------------------------------------------------------------------------------------------------------------------------- Shri P. B. Patil, Advocate for appellant.

Shri A. V. Bhide, Advocate for respondent No.1. Shri H. D. Dubey, AGP for respondent Nos.2 to 4. CORAM : A.S.CHANDURKAR, J.

DATE : APRIL 10, 2015 Prayer is to condone delay in filing the First Appeal. Reasons are mentioned in paragraph Nos.2 to 4 of the application.

Application is opposed by non-applicant No.1 on the ground that no reasonable explanation has been offered and there is considerable delay.

Considering the averments made in paragraph Nos.2 to 4 and treating them as acceptable, delay in filing the First Appeal is condoned subject to payment of costs of Rs.2000/- to the non-applicant No.1within period of four weeks from today.

C.A. is allowed in aforesaid terms and disposed of. JUDGE Asmita