Nandkishor Hansraj Gandhi v. The State Of Maha. Thr. Its Sec. For Urban Dev. Dept. Mantralaya Mumbai And ORS.
1 wp2592.25.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR WRIT PETITION NO.2592/2025 Nandakishor Hansraj Gandhi Vs. The State of Maharashtra and others Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's order and Registrar's orders.
Mr.S.M.Vaishnav, Advocate for petitioner.
Mr. D.P.Thakare, Addl. G.P. for respondent nos.1 and 3. CORAM : NITIN W. SAMBRE & SACHIN S. DESHMUKH, JJ. DATE : JUNE 16, 2025.
1.
Heard.
2.
There is no dispute that the work allotted to the petitioner is completed as per completion certificate (page 20 of the petition). The only question remains regarding payment to be made. The learned Assistant Government Pleader for the respondents/State, upon instructions, does not dispute the above position. The Government Resolution dated 20.10.2022 (pages 28 to 30 of the petition) indicates that the works listed therein have already been approved and completed and the payment is pending only for the receipt of funds.
3.
In view of the above admitted position that the work has been completed by the petitioner, we dispose of the writ petition by directing the respondents to make payment within a period of three months from today. (SACHIN S. DESHMUKH, J.) (NITIN W.SAMBRE, J.) Mukund Ambulkar