Exe. Engineer, M.I. Div.-2, Chikhli, Buldhana (Jigaon Rehabilitation Div. Khamgaon) And ANR v. Dadarao Namdeo Bagul (Dead) Thr. Lrs. Vatsala Dadarao Bagul And Others
(1) 52.fa.950.2022
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR FIRST APPEAL NO.950 OF 2022 Executive Engineer, M.I. Division-2, Chikhli, Dist. Buldhana and another Vs.
Dadarao Namdeo Bagul (Dead) Through L.R.'s 1) Vatsala Dadarao Bagul and others ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Mr. Nikhil A. Waghmare, Advocate for appellants. Mr. N. B. Kalwaghe, Advocate for respondent Nos.2 to 4. CORAM :
URMILA JOSHI-PHALKE, J.
DATED : 20/03/2023 Civil Application (CAF) No.2753/2022 1.
By this application, the applicants are seeking stay to the effect, operation, implementation and execution of the impugned Judgment and Award passed by the Joint Civil Judge Senior Division, Buldana in Land Acquisition Reference No.10/2016.
2.
On depositing the entire amount of compensation along with accrued interest including statutory benefits within ten weeks, the effect, operation, execution and implementation of the impugned Judgment and Award passed by the Joint Civil Judge Senior Division, Buldana in Land Acquisition Reference No.10/2016 be stayed till final disposal of the appeal. 3.
On failure to deposit the amount within above said period, the stay granted will be vacated automatically without further reference to the Court.
(2) 52.fa.950.2022 4.
Civil Application is disposed of.
FIRST APPEAL NO.
OF 20 Stand over after three weeks.
(URMILA JOSHI-PHALKE, J.) Sarkate SARKATE 16:40