← Library
Bombay High CourtPIL/119/2016dispossed offdismiss for default

Santosh S/O. Isram More v. State Of Maharashtra Thr. Secretary Dept. Of Village Development Of Village Development Mumbai And

2017-09-20Hon'Ble Shri Justice B. P. Dharmadhikari,Hon'Ble Shri Justice Arun Digambarrao Upadhye3 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

PUBLIC INTEREST LITIGATION NO. 119/2016.

Santosh Isram More -VERSUSState of Maharashtra and others.

Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders or directions and Registrar's orders.

CORAM : B.P. DHARMADHIKARI & ARUN D. UPADHYE, JJ.

DATE : SEPTEMBER 20, 2017.

Heard Shri S.U. Bhuyar, learned Counsel for the petitioner, Shri S.M. Ghodeswar, learned A.G.P. for respondent nos. 1,2 and 8, Shri S. Saoji, learned Counsel for respondent no.3 and 5 and Shri P.B.Patil, learned counsel for respondent nos. 6 and 7.

2.

After order of this Court dated 11.08.2016 and 28.06.2017, a written submissions has been filed by respondent no.3. Along with that submission, enquiry report dated 06.09.2016, prepared by Block Development Officer, Panchayat Samiti, Chikhili has been enclosed. Shri Bhuyar, learned counsel for petitioner is not satisfied with that report and he has

sought certain information under Right to Information Act. He is seeking adjournment.

3.

After hearing respective counsel for respondents, we find that the grievance is about alleged excessive expenditure or mis appropriation by the Gram Panchayat. Report of Block Development Officer needs to be looked into by respondent no.3 Chief Executive Officer. Chief Executive Officer can at that stage also extend opportunity of hearing to petitioner.

4.

Necessary records looked into by the Block Development Officer or then needed by the petitioner, can be made available at that juncture to him, and then suitable opportunity of hearing can be afforded. 5.

In this situation, we direct petitioner to appear before respondent no.3 Chief Executive Officer on 30.10.2017, and to abide by his further instructions in the matter. Said Authority shall consider report of Block Development Officer mentioned supra, hear all concerned and pass suitable orders within a period of next three months. If any amount is found recoverable, necessary action as per law shall then be initiated and amount shall be recovered within next four months.

6.

With these directions and with liberty to petitioner to approach again, if any other grievance arises, we dispose of the present Public Interest Litigation. No costs.

JUDGE JUDGE Rgd.