Bombay High CourtCAF/1451/2018admittedallwdgrantedrule absolute

The Executive Engineer, Minor Irrigation Division (Minor Irrigation Works), Nagpur v. Kamala Wd/O Ramesh Mankar (Deleted) And Others

2018-05-03Hon'Ble Shri Justice Z.A. Haq2 pages

1 caf1451.18

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR C.A.F. NO.1451/2018 IN C.A.F. NO.3683/2016 IN FIRST APPEAL STAMP NO.13508/2016 The Executive Engineer, Minor Irrigation Division (Minor Irrigation Works) Vainganga Nagar, Ajni, Nagpur ..Vs..

Kamala Wd/o Ramesh Mankar through L.Rs. and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Ms. A.M. Gupta, Adv. h/f Shri P.B. Patil, Adv. for the appellant. Shri R.S. Nagpure, Adv. for respondent Nos.1(a) to 1(d). Shri S.M. Ghodeswar, A.G.P. for respondent No.2. CORAM : Z.A. HAQ, J.

DATE : 3.5.2018.

Accepting the explanation given in the application, the appellant is permitted to deposit the cheque for the amount as per the impugned award. If the cheque is deposited within four weeks, interim order granted on 20th June, 2017 shall continue until further orders. Civil application is allowed accordingly. No costs.

C.A.F. NO.3683/2016 Accepting the explanation given in the application, delay of 632 days in filing the appeal is condoned. The civil application is allowed accordingly. No costs.

2 caf1451.18 FIRST APPEAL STAMP NO.13508/2016 Issue notice for final disposal, returnable on 13th August, 2018.

Shri R.S. Nagpure, Advocate waives notice for respondent Nos.1(a) to 1(d).

Shri S.M. Ghodeswar, A.G.P. waives notice for respondent No.2.

The learned Advocates for the respective parties state that the matter be placed before the National Lok-Adalat, Nagpur scheduled on 14th July, 2018.