Executive Engineer, (V.I.D.C.), Bembla Project Division, Yavatmal v. Dinesh Sureshchandra Jaiswal And 2 Others
1 908 caf 1409-2022
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO.1409/2022 IN FIRST APPEAL NO.495/2015 Executive Engineer, Bembla Project Division, Yavatmal Vs.
Dinesh Sureshchandra Jaiswal and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Ms Mallika Babhulkar, Advocate h/f M.A. Kadu, Advocate for appellant Shri A.B. Nakshane, for respondent No.1 Shri N.R. Patil, AGP for respondent No.2 CORAM :
SMT. M.S. JAWALKAR, J.
DATED :
01/07/ The appellant is directed to deposit the balance amount of compensation within a period of three months from passing of the order, however, due to administrative difficulties, there is delay. 2.
Learned Counsel for the appellant submits that the cheque is received. Permission is granted to deposit the same.
3.
For the reason mentioned in the application, the said application is allowed.
4.
Appellant is permitted to deposit the cheque of balance amount of compensation.
5.
Registry is directed to accept the same.
JUDGE Signed By:RANJANA SAMEER SAHARE R.S. Sahare