← Library
Bombay High CourtCAF/1263/2020ca disposed off

Vidarbha Irrigation Development Corporation, Bembla Project Division Through Ex. Engineer And ANR v. Jayashree Anil Mukkawar And Others

2020-10-22Hon'Ble Shri Justice S.M. Modak2 pages

F.A.465.2019 1/2

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR Civil Application (F) No.1263 of 2020 IN First Appeal No.465 of 2019 V.I.D.C. through Executive Engineer and Anr. Vs. Jayashree Anil Mukkawar & Ors. =-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Office notes, Office Memoranda of Coram, appearances, Court'

s orders Court's or Judge's Orders or directions and Registrar's orders.

=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-= Shri M.A. Kadu, Advocate for the Appellants.

Shri A.B. Nakshane, Advocate for Respondent No.1. Ms. Shamsi Haider, A.G.P. for Respondent Nos.2 to 4. CORAM : S.M. MODAK, J.

DATE : 22 nd OCTOBER, 2020.

Hearing was conducted through Video Conferencing and the learned counsel agreed that the audio and visual quality was proper. 2.

Heard learned Advocate Shri A.B. Nakshane for respondent No.1, learned Advocate Shri M.A. Kadu for the appellants and learned A.G.P. Ms. Shamsi Haider for respondent Nos.2 to 4. 3.

Perused the order dated 18th October, 2019 pertaining to disbursal of the 50% of the amount. Due to pandemic situation, this order could not be implemented. Respondent No.1 is desirous of getting the amount due to untimely run. Hence, the order:-

O R D E R

a) The Office is directed to do the personal verification of respondent No.1 and to comply with the formalities on 10th November, 2020 and to do the needful.

b) The civil application is disposed of.

F.A.465.2019 2/2 4.

This order be communicated to the counsel appearing for the parties, either on the email address or on WhatsApp or by such other mode, as is permissible in law.

JUDGE vijay