V. I. D. C. Through Executive Engineer, Purna Medium Project, Achalpur Division, Amravati v. Chitrabai Madhavrao Kadu And 2 Others
caf 3052 & 3053.2019.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR CIVIL APPLICATION (CAF) NO. 3052 OF 2019 with CIVIL APPLICATION (CAF) NO. 3053 OF 2019 in FIRST APPEAL (ST.) NO. 10842 OF 2019 [V.I.D.C. Vs. Chitrabai Madhavrao Kadu and ors.] ----------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoranda of Court's or Judge's Order Coram, appearances, Court's Orders or directions and Registrar's order__________________________________________________________ Shri A. M. Kukday, Advocate for the appellant Ms. Shamsi Haider, AGP for respondent nos. 2 and 3. CORAM : M. G. GIRATKAR, J.
DATE : 14/08/2019 Heard learned Counsel Shri Kukday for the appellant.
Issue notice to the respondents returnable on 11.09.2019.
Ms. Shamsi Haider, learned AGP waives notice on behalf of respondent nos. 2 and 3.
The appellant is permitted to deposit the balance amount of compensation before this Court within a period of six weeks.
CIVIL APPLICATION (CAF) NO. 3053 OF 2019 Heard.
Stay is granted to the impugned judgment subject to deposit of balance amount of compensation before this Court within a period of six weeks.
JUDGE SMGate