IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR WRIT PETITION NO. 4225/2011 MSEDCL .Vs. M/s. Shrikrishna Ginning and Pressing Factory and arn. --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Mr. S. V. Purohit, Advocate for petitioner.

CORAM :

ANIL L. PANSARE, J.

DATE :

SEPTEMBER 30, 2024 The petition was admitted to consider whether infrastructure cost, which was earlier levied for the purpose of giving electricity connections by the Maharashtra State Electricity Distribution Company Limited (M.S.E.D.C.L.), was permissible.

2.

It is stated that this issue was a subject matter in Civil Appeal No.4305/2007 (Maharashtra State Electricity Distribution Co. Ltd. Vs. Maharashtra Electricity Regulatory Commission and another) before the Hon'ble Supreme Court, which has been decided on 10/11/2016, by which the imposition of infrastructure cost has been quashed. 3.

In the light of above, the petitioner shall refund the infrastructure cost as received by them while granting application seeking electricity connection, if the cost is not already refunded.

4.

The petition is accordingly disposed of. Rule stands discharged. No order as to costs.

(Anil L. Pansare, J.) Kahale