Trimurti Construction Company Through Partner, Shri Satish Shyamlal Bachwani v. State Of Maharashtra, Through Secretary, Urban Development Department, Mumbai And Another
1 wp4368.19.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR WRIT PETITION NO.4368 OF 2019 [Trimurti Construction Company .vs. State of Maharashtra and others] ........................................................................................................................... Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders ................................................................................................................................................................. Shri I.N. Choudhari, Advocate for the petitioner, Ms N.P. Mehta, AGP for respondent no.1.
..........
Coram :
R.K. Deshpande & Vinay Joshi, JJ.
Date : 25.06.2019.
Heard.
The petitioner was allotted work of construction of shopping complex on 12.9.2012 and according to the petitioner the site was not made available and, therefore, the work could not be executed. Now the Municipal Council has again issued tender notice dated 31.5.2019 in respect of the same work. Hence, this petition is filed challenging it on the ground that the petitioner has already allotted the said work but the site was not made available. The petitioner has an remedy to file a Civil Suit for breach of contract or shall be at liberty to submit his bid in response to the advertisement. We do not find any reason to entertain this petition. The writ petition is dismissed.
(Vinay Joshi, J.) (R.K. Deshpande, J.) Gulande