Executive Engineer, Bembla Project Division, Yavatmal v. Vasantkumar S/O Shantilal Ostwal And 2 Others
caf.2638.17.odt 1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR CIVIL APPLICATION (F) NO.2638 OF 2017 IN FIRST APPEAL NO. 915 OF 2016 ( V.I.D.C. through the Executive Engineer, Bembla Project Dn.Yavatmal..vs.. Vasantkumar Shantilal Oswal and others ) --------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoramda of Coram, appearances, Court's orders of directions Court's or Judge's orders.
and Registrar's Orders.
--------------------------------------------------------------------------------------------------------------------------------- Shri V.G.Palshikar, Advocate for applicant.
Shri A.B.Nakshane,Advocate for non-applicant no.1. CORAM: SMT. DR. SHALINI PHANSALKAR-JOSHI, J.
DATE: 2 nd August, 2017.
This is an application preferred by original claimant seeking withdrawl of the amount of compensation which is total to the tune of Rs. 5,48,707/- which is deposited in the Court.
Subject to the condition of non-applicant no.1 furnishing usual undertaking that the entire amount of compensation will be returned with interest subject to decision before this Court. The respondent no.1 is permitted to withdraw 75% of the decretal amount. The application is accordingly disposed of.
JUDGE Kitey