IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

CIVIL APPLICATION (CAF) NO.729 OF 2025 IN FIRST APPEAL STAMP NO.12060 OF 2024 Laxman Motiram Gayanar (dead) through LRs Vs. The Executive Engineer, Lower Wardha Project Division, Wardha & others __________________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's orders.

and Registrar's Orders.

Shri V.N. Patre, Advocate for appellant.

Shri Uday Gosavi, Advocate for respondent no.1. Shri Mangesh Kadu, AGP for respondent nos.2 & 3. CORAM : M.W. CHANDWANI, J.

DATE : 07.05.2025.

1.

This is an application for condonation of delay of 3483 days caused in preferring the first appeal for enhancement of compensation in land acquisition. 2.

For the reasons mentioned in the application, the delay is condoned. However, it is made clear that the appellant shall not be entitled for interest on the enhanced amount of compensation and other statutory benefits on the delayed period, if the appeal is allowed. Appeal be registered.

3.

The application stands disposed of.

FIRST APPEAL STAMP NO.12060 OF 2024 4.

Shri Uday Gosavi, learned counsel waives service of notice for respondent no.1.

5.

Shri Mangesh Kadu, learned AGP waives service of notice for respondent nos.2 and 3.

JUDGE Wagh