IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR C.A.F. NO.3469/2017 IN FIRST APPEAL STAMP NO.13027/2017 Executive Engineer (V.I.D.C.) Bembla Project Division, Yavatmal and another ..Vs..

Prabhavati W/o Chandrashekhar Thakre and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri M.A. Kadu, Advocate for the appellants.

CORAM : Z.A. HAQ, J.

DATE : 17.4.2018.

The learned Advocate for the appellants states that the cheque for the amount of compensation is ready and it can be deposited within a week. Accepting the submission, it is directed that execution of impugned award shall stand stayed until further orders. The civil application is allowed accordingly. No costs. JUDGE Tambaskar.