2023:BHC-NAG:12909 1 14.caf.2529.2023

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

CIVIL APPLICATION (CAF) NO. 2529 OF 2023 IN FIRST APPEAL (ST.)NO. 12261 OF 2023 Maharashtra State Power Generation Co. Ltd., Akola VS.

Mohd. Ayyaz Abdul Munaf and others _______________________________________________________________ Office Notes, Office Memoranda of Coram, appearances, Court's orders of directions Court's or Judge's orders.

and Registrar's Orders.

Mr N. G. Moharir, Adv. h/f. Mr G. E. Moharir, Advocate for the appellant Mr S. S. Sohoni, Advocate for respondent Nos. 1 to 3 Mr M. A. Kadu, AGP for the State CORAM :

G.A. SANAP, J.

DATE :

AUGUST 30, 2023.

Heard learned Advocates for the parties..

2.

This is an application for condonation of 22 days delay in filing first appeal against the judgment and award dated 16.02.2023.

3.

The reasons have been stated in the application. In view of the reasons, the application is allowed. 4.

The delay of 22 days caused in filing the first appeal stands condoned.

5.

The appeal be registered.

6.

The application stands disposed of, accordingly.

2 14.caf.2529.2023 CIVIL APPLICATION No.2530 of 2023 7.

Heard learned Advocate for the appellant.

8.

Perused the application. The reasons have been stated in the application.

9.

In view of the reasons stated in the application, subject to deposit of the entire amount of compensation within eight weeks, there shall be stay to the execution of impugned judgment and award dated 16.02.2023 passed by the Civil Judge Senior Division, Akola in Land Acquisition Case No. 123 of 2013.

10.

The application stands disposed of, accordingly. (G. A. SANAP, J.) Namrata