Executive Engineer, Bembla Project Division Vidarbha Irrigation Development Corporation, Yavatmal v. Uttam Ishnaji Wanjari And Others
caf 2563.2019.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR PURSIS STAMP NO. 9010 OF 2019 with CIVIL APPLICATION (CAF) NO. 2563 OF 2019 in FIRST APPEAL (FA) NO. 1148 OF 2017 [Executive Engineer, Bembla Project Division, Yavatmal Vs. Uttam Ishnaji Wanjari and ors] ----------------------------------------------------------------------------------------------------------------------------------- Office Notes, Office Memoranda of Court's or Judge's Order Coram, appearances, Court's Orders or directions and Registrar's order__________________________________________________________ Shri P. B. Patil, Advocate for the appellant Shri K. S. Narwade, Advocate for respondent no. 1/applicant Ms. M. S. Naik, AGP for respondent nos. 2 and 3. CORAM : M. G. GIRATKAR, J.
DATE : 11/07/2019 Heard learned Advocate Shri Narwade for respondent no. 1/applicant.
Shri Patil, learned Advocate for the appellant pointed out order passed by this Court dated 11.10.2017. As per order dated 11.10.2017, Respondent no.1/claimant/Land owner was permitted to withdraw 50% amount.
Shri Narwade, learned Advocate for respondent no. 1/applicant pointed out Sale Deed of plot purchased by the respondent no. 1/applicant and submitted that he wanted to construct his house on the said plot. Looking to the grounds mentioned in the application, respondent no. 1/applicant is permitted to
caf 2563.2019.odt withdraw 25% amount deposited in fixed deposit on furnishing solvent surety of like amount to the satisfaction of the Registrar (Judicial).
The application is disposed of.
JUDGE SMGate