Executive Engineer Minor Irrigation Project Pusad Tah. Pusad Yavatmal v. Karandas Bhura Chouhan And Others
1207 CAF 32-2017 (CAF 2733-2017) 1/1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
C.A.F. No. 2733/2017 IN FIRST APPEAL ST. No. 12428/2016 (EXE. ENGINEER, MINOR IRRIGATION PROJECT, PUSAD, DISTT. YAVATMAL -vs- KASANDAS BHURA CHOUHAN AND OTHERS) ------------------------------------------------------------------------------------------------------------------------------------ Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.
or directions and Registrar's orders.
None present for appellant.
Shri N.M. Kolhe, counsel for respondent no.1. CORAM: DR. SMT. SHALINI PHANSALKAR-JOSHI, J.
DATE : JULY 12, 2017.
Heard learned counsel for the claimantrespondent no.1. Learned counsel for appellant absent when called out twice.
This is an application for withdrawal of the amount of compensation deposited in the court. As he application is not resisted at all, in view thereof, for the reasons given in the application, as sufficient cause is made out, application is allowed. The claimant-respondent no.1 is permitted to withdraw the entire amount of compensation, subject to furnishing of usual undertaking and also the solvent surety/security for 50% of the said amount.
Application is disposed of accordingly.
JUDGE Yenurkar