← Library
Bombay High CourtCAF/2734/2017admittedallwdgrantedrule absolute

Executive Engineer Minor Irrigation Project Pusad Tah. Pusad Yavatmal v. Sadashiv Hari Chouhan And Others

2017-07-12Hon'Ble Dr. (Smt.) Justice Shalini Phansalkar-Joshi1 pages

1207 CAF 21-2017 (CAF 2734-2017) 1/1

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR.

C.A.F. No. 2734/2017 IN FIRST APPEAL ST. No. 12410/2016 (EXE. ENGINEER, MINOR IRRIGATION PROJECT, PUSAD, DISTT. YAVATMAL -vs- SADASHIV HARI CHOUHAN AND OTHERS) ------------------------------------------------------------------------------------------------------------------------------------ Office notes, Office Memoranda of Coram, appearances, Court's orders Court's or Judge's Orders.

or directions and Registrar's orders.

None present for appellant.

Shri N.M. Kolhe, counsel for respondent no.1. CORAM: DR. SMT. SHALINI PHANSALKAR-JOSHI, J.

DATE : JULY 12, 2017.

Heard learned counsel for the claimantrespondent no.1. Learned counsel for appellant absent when called out twice.

This is an application for withdrawal of the amount of compensation deposited in the court. Considering the reasons given in the application, claimant-respondent no.1 is permitted to withdraw the entire amount of compensation, subject to furnishing of usual undertaking and also the solvent surety/security for 50% of the said amount.

Application is allowed and disposed of accordingly.

JUDGE Yenurkar