IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR CIVIL APPLICATION (C.A.F.) NO.2769/2016 IN FIRST APPEAL NO.1102/2012 Vidarbha Irrigation Development Corporation, through its Executive Engineer, Bembla Project, Yavatmal ..VS..

Purushottam R. Gulwade and others - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Shri A.B. Patil, Adv. for the appellant.

Shri K.S. Narwade, Adv. for respondent No.1.

Mrs. A.R. Kulkarni, A.G.P. for respondent Nos.2 and 3. CORAM : Z.A.HAQ, J.

DATED : 24.8.2016.

Accepting the reasons stated in the application, the appellant is granted four weeks' time to deposit the amount. The civil application is allowed accordingly. JUDGE Tambaskar.

2 caf2769.16 CERTIFICATE original signed Judgment/Order".

Uploaded By : N.V. Tambaskar.

Uploaded On : 24.8.2016.